Step 2: Securing angle brackets to the newel posts:
Determine the placement of your top rail and bottom rail. The information you will need to do this is:
- Height of baluster (not including pipe)
- Height of the bottom rail
- Distance of bottom rail from the substrate (surface).
Locate the following components from your hardware kit:
- Aluminum angles (4 per newel post)
- 1/4" Hex Head Bolt (x8) or 1/4" threaded rod (x4)
- 1/4" Hex Head Nut (x8)
- Lock washers (x8)
Mark the position of the aluminum angle on the face of the newel post. Keep in mind that the angles mount to the underside of the rails. Drill (4) four 1/4" dia. holes in the locations where the brackets are to be mounted. Be sure the holes pass through the uPVC pipe of the newel post. Secure the brackets to the newel post as indicated in the diagram with bolts, washers and nuts provided in the hardware kit. |